Nscale is building a large AI data centre campus at Kvandal outside Narvik, linked to the Stargate Norway initiative with Aker and OpenAI. Phase 1 is about 230 MW and the full campus up to 520 MW. HENT is the main contractor and in September 2026 signed for two more buildings adding 75 MW.
In spring 2026 about 350 people worked on site, and the workforce is expected to grow to at least 1,500. Narvik has a small rental market, so crews need housing planned well ahead.
- Up to 1,500
- Workers on site as the build ramps up
- 230 MW
- Phase 1
- 520 MW
- Full campus
- Stage
- Under construction
- Client / owner
- Nscale (Aker Nscale JV; Stargate Norway with OpenAI)
- Main contractors
- HENT (Sentia)