Microsoft is expanding its Swedish cloud region with data centres in Gävle and Sandviken, on land bought from both municipalities. Construction is ongoing in Gävle in 2026 with large international crews on site. In Sandviken, Microsoft paused its large data hall build in April 2025 because the power connection depends on closing Rörberg airport.
Swedish media have reported poor living and working conditions for some foreign crews on the build. Good, documented housing close to the site is part of how contractors protect their people and their reputation.
- Gävle
- Construction ongoing
- Sandviken
- Paused since April 2025
- 3-on/1-off
- Typical rotation in recruiter ads
- Stage
- Under construction
- Client / owner
- Microsoft