Microsoft is building a Helsinki-area data centre region on three campuses in Espoo, Kirkkonummi and Vihti, with waste heat going to Fortum's district heating network. Phase 1 started in late 2024, and in April 2026 Microsoft confirmed phase 2 with building permits in place on all three sites. Microsoft expects around 7,500 people on site at the construction peak.
Microsoft reported more than 3,500 workers on site in April 2026, rising towards about 7,500 at the construction peak. The three campuses lie west of Helsinki, so teams can live in Espoo, Kirkkonummi, Vihti or Helsinki.
- Up to 7,500
- People on site at peak
- 3
- Campuses (Espoo, Kirkkonummi, Vihti)
- Phase 2
- Under way in 2026
- Stage
- Under construction
- Client / owner
- Microsoft